Boardwalk Access Control Project

boardwalkHercules will be adding force protection at 28 separate locations including the inlet lot/end of the board walk. More specifically, we will be furnishing and installing (302) M30 fixed or removable bollards, (8) M30 manual crash beams with the option to turn electric operable and (760) feet of passive cable barrier. All crash rated products are to be white in color so it can “blend in” and meet the city’s aesthetic expectations.

We have estimated that this scope will take more than 300 days to complete. However, the project schedule requires completion before Memorial Day (+/- 140 days from now). Therefore, we will be doubling, and in most cases tripling, our on-site man power, equipment and supervision to work sites concurrently so we can achieve substantial completion before Memorial Day.